Billed$3,907,000
Left to bill$215,000
Complete95%
Near contract cap — review all subcontractor COs before final draw.
- Final plumbing inspections — units 3 & 4
- Reconcile remaining subcontractor invoices
- Touch-up paint in common hallway
- Schedule final walkthrough with client
- Submit final AIA draw request
Structural reinforcement — discovered rot in joistsbilled
2026-04-20Upgraded condo unit fixtures (client request)approved
2026-05-28
Old Market Condo Rehab
2026-06-17 · Mike T.- Unit 3 — cabinets installed
- Unit 4 — plumbing fixtures set
- Common hallway — touch-up paint needed