Progress

  • Ferrer Residence
    2026-06-19 · Mike T.
    video
    • Plumbing rough-in — master bath complete
    • Kitchen supply lines stubbed
    • Front yard grading — 60% complete
  • Old Market Condo Rehab
    2026-06-17 · Mike T.
    photo
    • Unit 3 — cabinets installed
    • Unit 4 — plumbing fixtures set
    • Common hallway — touch-up paint needed
  • Pioneer Hills Spec
    2026-06-15 · Corey
    photo
    • Drywall finish complete — main floor
    • HVAC ducts visible — not yet balanced
    • South elevation siding — 40%