Billed$1,263,000
Left to bill$430,000
Complete76%
Client leaving for Maine — selections deadline this week.
- Finish plumbing rough-inMike T.
- Order windows (Andersen package)Corey
- Grade front yardCrew
- Complete interior selections before client tripCorey
- Schedule cabinet install for next weekMike T.
Upgraded kitchen island — larger footprint + quartzapproved
2026-05-12Added exterior stone veneer at entrypending
2026-06-03
Master bath floor tilepending
Ferrer Residence · TileInterior door hardware — matte blackselected
Ferrer Residence · HardwareKitchen pendant lights (3)ordered
Ferrer Residence · LightingKitchen island quartz — upgradedselected
Ferrer Residence · Countertops
Ferrer Residence
2026-06-19 · Mike T.- Plumbing rough-in — master bath complete
- Kitchen supply lines stubbed
- Front yard grading — 60% complete
Back to jobs